US Army Opens Land Near Ammo Depots for AI Data Centers, Requiring On-Site Power Generation
The U.S. Army issued a request for proposals on November 19, 2026 — or November 20, 2026, according to Holland & Knight — for commercial power generation facilities, with an option to include data centers, at nine military installations across the country [2][3]. The solicitation marks a shift from earlier rounds that led with data center siting: this time, proposals for data centers alone will not be considered. Every project must include power generation capable of delivering contingency electricity to the host base within one hour of a grid outage and sustaining it for at least 14 continuous days [2][6].
The nine sites include Blue Grass Army Depot in Kentucky (a major munitions storage facility), Tooele Army Depot in Utah (an ammunition hub), and Sierra Army Depot in California (a long-term equipment storage installation), along with Fort Bragg (North Carolina), Fort Hood (Texas), Fort McCoy (Wisconsin), Fort Rucker (Alabama), Pine Bluff Arsenal (Arkansas), and Joint Base Lewis-McChord (Washington) [1][6]. Proposals are due January 18, 2027. Site tours begin November 30 and continue at individual installations through December 17, with registration deadlines of November 25, December 2, and December 9 depending on the installation [2].
From data-center-first to energy-first
The Army's January 2025 call for data center development on four military bases. A June 2025 RFP sought power generation at seven eastern installations, with conditional awards at six announced in September [3]. In March 2026, the Army conditionally selected Carlyle for roughly 1,384 acres at Fort Bliss, Texas, and CyrusOne for about 1,201 acres at Dugway Proving Ground, Utah; neither lease has been finalized [3][5].
The new RFP reflects two realities, according to Beveridge & Diamond, the law firm that analyzed the solicitation: the nation needs new generation regardless of data center politics, and military installations may offer developers reduced exposure to local land-use restrictions and greater predictability in approvals [2]. The Army's first preference for any data center component is hardened facilities built to ICD 705 standards for Top Secret/IL6 workloads, followed by hyperscale AI and high-performance computing facilities targeting a power usage effectiveness of 1.15 or less [2][6].
Lease terms and developer obligations
The Army will use its enhanced-use lease authority under 10 U.S.C. § 2667, offering an initial 25-year term with possible renewals [2][6]. Consideration must equal or exceed fair market rental value, with a preference for in-kind contributions such as the resilience power itself [2][6]. Developers must be U.S.-organized entities with majority domestic ownership and control, and must finance the full project lifecycle — including environmental review, construction, operations, and decommissioning — without Army capital [2][6].
The Army will not purchase power or computing capacity; developers must secure their own third-party offtakers [2][3][6]. Eligible generation technologies include advanced nuclear reactors (up to 500 MW per unit) [3], natural gas turbines, fuel cells, hydrogen systems, battery storage, and solar paired with dispatchable generation and storage [2][6].
Site constraints: contamination, water, and jurisdiction
Several parcels carry significant environmental complications. At Blue Grass, a major munitions storage facility, the 358-acre plot has a 69 kV transmission line crossing it but lacks water distribution lines [1]. Tooele's three parcels (36, 96, and 500 acres) include groundwater plumes contaminated with trichloroethylene (TCE) on the smallest and largest plots, blocking new well drilling [1]. Sierra Army Depot's four parcels total 445 acres, served by Plumas Sierra Rural Electric Cooperative and a Tuscarora gas pipeline [1]. Fort Bragg's three parcels (385 acres total) are undeveloped mixed forest with high water risk; Duke Energy provides transmission and Piedmont Natural Gas has an adjacent pipeline [1]. Fort Rucker offers 903 acres across three parcels with Alabama Power and Southeast Alabama Gas District service [1].
Documents for Fort McCoy, Fort Hood, and Joint Base Lewis-McChord were removed from the procurement notice, limiting public information on those sites [1].
Water use must be net-neutral or better, sourced from non-potable alternatives such as industrial grey water, treated municipal wastewater, or closed-loop cooling towers [4][6]. Projects must avoid drawing on aquifers [6].
The leases are federal actions subject to NEPA, the National Historic Preservation Act, and the Endangered Species Act. Some installations operate under exclusive federal legislative jurisdiction, which may limit state and local regulatory authority — though the RFP notes developers may still face state and local operational permitting requirements [2][6].
Political tailwinds and headwinds
The push to open federal land for data centers began under the Biden administration and has continued under the Trump administration [1]. A July 2025 Trump executive order directed the Interior and Energy departments to offer authorizations for data center sites on lands they manage [4]. However, Senator Ruben Gallego has filed a defense-bill amendment that would bar new privately operated data centers on military installations, with exceptions for Defense Department national security facilities; it has not been voted on [3].
The Army's November RFP expressly requires data center developers to describe community outreach plans, assess potential opposition, and explain how they would address concerns — an acknowledgment that federal siting does not insulate projects from local pushback [2].
What happens next
Site tours begin November 30, with registration deadlines staggered through December 9 depending on the installation [2]. Questions are due January 6, 2027; proposals are due January 18 at 5:00 p.m. ET [2][6]. The Army may award one or more leases, and may select multiple offerors at the same installation if projects can be accommodated without conflict [6].
For developers, the calculus is whether the strategic advantages — predictable federal process, physical security, co-located generation, and potential relief from local opposition — outweigh the complexities of federal leasing restrictions, environmental review, supply chain rules, and the requirement to bring their own customers and capital [2]. The Army's objective, as stated in the RFP, is to maximize the financial return to the Department of the Army through the lease of non-excess available land on the installations [6].
Sources
- US Army offers more land to private AI data centers, across nine sites (datacenterdynamics.com)
- U.S. Army Seeks Power Generation and Data Center Development at ... (bdlaw.com)
- US Army offers land at nine more bases for power plants and AI data centers ... (mlq.ai)
- Army Seeks Power Projects, Eyes Data Centers (yahoo.com)
- Army reaches conditional agreement with private industry for hyperscaled data centers | Article | The United States Army (army.mil)
- SAM.gov (sam.gov)